Time Optimization Technique Using Reliable Commitment Model

Authors

  • P. Surekh PG Student, Department of Civil Engineering, RVS Technical Campus, Coimbatore, Tamil Nadu, India
  • A. Varadharaj Assistant Professor, Department of Civil Engineering, RVS Technical Campus, Coimbatore, Tamil Nadu, India

DOI:

https://doi.org/10.51983/tarce-2017.6.2.2239

Keywords:

Construction Projects, Variability, WIP Buffers, Multiple Linear Regression, Reliable Commitment Model

Abstract

Construction is a very complex process and nearly every single project is unique. The resulting number of parts, relative lack of standardization, multiple participants and constraining factors make construction projects a difficult endeavour. Adding to this complexity is the high degree of interdependency inherent to the construction process. Complexity can be defined as “something made up of closely connected parts which are difficult to explain or understand, or a number of different parts intricately related”. Due to the inherent complexity, uncertainty, and variability of the construction process, it is important to study the root causes of time buffer used to protect against those challenging characteristics. Reliable Commitment Model, RCM, a new decision-making tool, using statistical models to develop more reliable work plans at the operational level in repetitive projects. RCM increases planning reliability, reduces variability, and promotes a continuous workflow with short waiting times. The main objective is to study the potential improvement on project performance when using RCM to manage WIP buffers at the site or operational level. Worker weeks and process progress are used as the main performance measures in a repetitive building project. RCM analyses the problems of planning process at the operational level shows that one of the most important reason for non-completion of weekly plans in repetitive project is the lack of WIP. RCM predicts the process progress by using variables such as Worker weeks, WIP buffer and planned progress, using Multiple Linear Regression (MLR) at the operational level.

References

Vicente Gonzalez; Luis F. Alarcon; Sergio Maturana; Fernando Mundaca; and Jose Bustamante, “Improving Planning Reliability and Project Performance Using the Reliable Commitment Model”, Journal of Construction Engineering and Management, 010.136:1129-1139.

Vicente Gonzalez; Luis Fernando Alarcon; Sergio Maturana; and Jose Antonio Bustamante, “Site Management of Work-in-Process Buffers to Enhance Project Performance Using the Reliable Commitment Model: Case Study”, Journal of Construction Engineering and Management, Vol. 137, No. 9, September 1, 2011. ©ASCE, ISSN 0733-9364/2011

Vicente Gonzalez, Luis Fernando Alarcon, Sergio Maturana, Fernando Mundaca and Jose Antonio Bustamante, “Rational Commitment Model: Improving Planning Reliability And Project Performance”, Proceedings for the 17th Annual Conference of the International Group for Lean Construction

B. W.Wambeke, S. Hsiang and M. Liu, “Causes of Variation in Construction Project Task Starting Times and Duration.” J Constr. Eng. And Mgmt., Vol. 137, No. 9, September, pp. 663-677, 2011.

Vicente Gonzalez, Luis Fernando Alar con, Sergio Matur ana, Jose Antonio Bustamante and Fernando Mundaca, “Work-in-process Buffer Management using the Rational Commitment Model in Repetitive Projects”, Proceedings for the 16th Annual Conference of the International Group for Lean Construction, Production Planning and Control.

V. Gonzalezab, L.F. Alarcona and F. Mundacac, “Investigating the relationship between planning reliability and project performance”, Production Planning & Control, ISSN 0953–7287, 2008.

Gonzalez, V. Alarcon, L.F, Ulloa, H., RCM-Plan: A Computer Prototype for Improving Planning Reliability from a Lean ProductionViewpoint”, Journal of Construction Engineering and Management, 2008.

V. Gonzalez , L.F. Alarcon and K. Molenaar, “Multi-objective design of Work-In-Process buffer for scheduling repetitive building projects”, Automation in Construction Vol. 18, pp. 95–108, 2009

Vicente Gonzalez, Luis Fernando Alarcon and Pedro Gazmuri “Design of Work in Process Buffers in Repetitive Building Projects: A Case Study”, Proceedings of the 14th International Conference for Lean Construction, Santiago, Chile, July 25th – 27th

V. Gonzalez, L. Rischmoller and L.F. Alarcon, “Design of buffers in repetitive projects: using production management theory and IT tools”, Proceedings of 4th International Postgraduate Research Conference, University of Salford, Manchester, UK, 2004.

Downloads

Published

05-11-2017

How to Cite

Surekh, P., & Varadharaj, A. (2017). Time Optimization Technique Using Reliable Commitment Model. The Asian Review of Civil Engineering, 6(2), 23–30. https://doi.org/10.51983/tarce-2017.6.2.2239